Key takeaways
- Schedule H and Schedule G split your purchase price into 13 stages worth 2.5% to 15% each, triggered by construction milestones, not fixed dates.
- Your bank releases loan money to the developer stage by stage, and you usually pay interest only on the amount already released.
- Your instalment jumps from a small interest-only sum to a full principal-and-interest payment the moment you get vacant possession.
- The last 5% of the price sits with the lawyer as stakeholder money, released in two 2.5% instalments 6 and 18 months after possession.
Say you buy a new condo for RM600,000 that is still 30 months from completion. You might assume you pay nothing until you get the keys. In reality, your bank can start charging you interest within weeks of signing, long before a single wall goes up.
That is because Malaysian new launches run on two linked systems: the developer's progressive payment schedule and your bank's end financing. Together they decide how much you actually pay each month while the building is still a hole in the ground.
This guide walks through both, with a worked example, so you know what your monthly cash flow looks like before you sign anything.
What is the progressive payment schedule?
Most new launches use the standard Sale and Purchase Agreement (SPA) set out in the Housing Development (Control and Licensing) Regulations 1989: Schedule H for apartments, condos and other strata property, and Schedule G for landed homes. Both schedules, as published by the National House Buyers Association (HBA), currently split your purchase price into the same stages, each tied to a construction milestone rather than a calendar date.
- 10% on signing the SPA
- 10% when foundation work (piling and below-ground work) is done
- 15% when the structural framework and floor slab are done
- 10% when walls, door and window frames go up
- 10% when roofing, ceiling, wiring and plumbing (without fittings) are done
- 10% on internal and external plastering
- 5% each for sewerage, drains and roads serving the building (15% total)
- 12.5% when you take possession with water and electricity ready to connect
- 2.5% when the subdivision application is submitted and accepted
- 5% held by your lawyer as stakeholder money, released 2.5% six months after vacant possession and 2.5% at 18 months
How does end financing fit into this?
Your home loan, called end financing, does not pay out in one lump sum. Each time the developer certifies a stage and bills you under Schedule G or H, your bank releases, or disburses, that percentage of your approved loan directly to the developer.
Until vacant possession, most banks charge you interest only on the amount they have actually disbursed so far, not on your full loan amount. This is sometimes called progressive interest. Once you get vacant possession, your bank switches you to a full principal-and-interest instalment on the whole loan, usually whether or not the final 5% stakeholder sum has been fully released yet.
What does this look like in real numbers?
Say you buy a RM600,000 condo with a 90% loan, so RM540,000 is financed, at an illustrative home loan rate of 4% a year over 30 years. This is a worked example to show the shape of the cash flow, not a quote, so check your own bank's rate and terms.
- On signing (10% billed): about RM54,000 of your loan is disbursed. Interest-only works out to roughly RM180 a month.
- After the structural framework stage (35% billed in total): about RM189,000 disbursed, interest-only around RM630 a month.
- After plastering (65% billed in total): about RM351,000 disbursed, interest-only around RM1,170 a month.
- After roads, drains and sewerage (80% billed in total): about RM432,000 disbursed, interest-only around RM1,440 a month.
- At vacant possession (around 92.5% billed): about RM499,500 disbursed, interest-only around RM1,665 a month.
- From vacant possession: your instalment switches to a full principal-and-interest payment on the full RM540,000 loan, which works out to roughly RM2,580 a month over the remaining tenure.
That is a jump of around RM900 a month in this example, in a single billing cycle, with no change in the loan amount itself, only in how it is being repaid.
What are the best tips for managing cash flow during progressive payments?
- 1Budget for interest from day one. Even a small interest-only sum, often just a few hundred ringgit, starts hitting your account weeks after you sign the SPA, long before completion.
- 2Track the construction progress, not the calendar. Schedule G and H stages are tied to actual work done, so ask for the latest progress report before assuming the next bill is due.
- 3Check whether your bank needs your sign-off on each claim. Some banks require you to confirm a progress claim before releasing funds, and a missed confirmation can delay the developer's billing.
- 4Stress-test your budget for the jump at vacant possession. Your payment can rise several times over in one month, so plan around the full instalment, not the smaller interest-only figure.
- 5Keep cash aside for the final 5%. The two 2.5% stakeholder payments, due 6 and 18 months after vacant possession, are tied to the subdivision and strata title process and are separate from your monthly instalment.
- 6Do not pick landed over strata, or the other way round, because of the payment schedule. Schedule G and Schedule H currently use the same percentages, so the schedule itself should not be the deciding factor.
Bottom line
Progressive payment and end financing work together: the developer bills you in the same stages whether you buy landed or strata, and your bank releases loan money, and charges you interest, to match. The real jump in cost comes at vacant possession, when a small interest-only sum turns into a full instalment overnight.
Before you sign a new launch SPA, ask your bank for the exact instalment you will pay the month after vacant possession, not just the rate during construction. That one number tells you whether the project still fits your budget once the building is actually done.
Frequently asked questions
What is Schedule H in a Malaysian property purchase?
It is the standard payment schedule in the Sale and Purchase Agreement for strata property such as condos and apartments, set under the Housing Development (Control and Licensing) Regulations 1989. It splits your purchase price into stages tied to construction milestones.
Is Schedule G the same as Schedule H?
Schedule G covers landed property and Schedule H covers strata property, but both currently use the same percentages at each stage, according to the National House Buyers Association's published schedules.
Do I pay full instalments while my new launch is under construction?
Usually not. Most banks charge interest only on the portion of your loan already disbursed to the developer, so your payment is smaller during construction and jumps to a full instalment at vacant possession.
When is the last part of the purchase price paid?
The final 5% is held by the developer's solicitor as stakeholder money and released in two instalments of 2.5% each, six and 18 months after you get vacant possession.
What are your top tips for managing progressive payments on a new launch?
Budget for interest from the day you sign, track the construction progress report rather than the calendar, and ask your bank for the exact instalment you will pay from vacant possession.